S-Bahn | 14-month Ringbahn closure for bridge replacement in Berlin-Friedrichshain
The railway bridge over Belt Street, built in 1910, must be replaced by a new building. Deutsche Bahn plans to start construction in 2030.
Deutsch (original) ·Auto-translated to English
The bridge over the Belt Road needs to be replaced. The replacement is to be installed in the green strip between the railway tracks and the snake-like block of residential buildings. Photo: SenStadt (DL-DE->Zero-2.0) Something is coming to the passengers of the Ringbahn - and the residents will also have to carry their burden. Because Deutsche Bahn is planning to demolish and rebuild the bridge over Belt Street in Berlin-Friedrichshain, immediately south of Frankfurter Allee. In addition, two other bridges on the tracks branching off from the ring towards Rummelsburg also need to be replaced. These are the crossings of Wartenbergstrasse and Tasdorfer Strasse that are already in Lichtenberg.
The findings in the documents from the planning approval process are clear. The bridge over the Belt Road, built in 1910, “is showing significant damage, so that its long-term availability can no longer be guaranteed,” it is said. The other two bridges from 1927 have also “reached their useful life and need to be replaced.”
The biggest chunk is the bridge over the Belt Road. On behalf of the railway infrastructure operator DB Infrago, various variants were tested, both in terms of the bridge type and the construction process. As a result, two tie arch bridges over 65 meters long are to be built, one each for the track pairs of the S-Bahn and long-distance railway. A high arch ensures stability in such steel bridges.
The result of the considerations is also that the bridges for the long-distance train and S-Bahn should be demolished and rebuilt at the same time. This results in the shortest overall construction time of 20 months. And the 14-month total closure of the two pairs of Ringbahn tracks would only be half a month longer than variants in which the S-Bahn tracks would be pivoted onto the long-distance railway line during construction. The closure is scheduled to begin in the third quarter of 2030 and end in the third quarter of 2031. The total construction time for other variants would be significantly longer and there would be additional difficulties such as single-track closures for months.
With the exception of the phases of demolition and the lifting of the new bridges, traffic on the Belt Road can largely continue. This is also important for the replacement bus service between the Frankfurter Allee and Ostkreuz train stations, which would otherwise have to take long detours, according to the documents. "Most of the time, at least single-lane car traffic should be maintained in both directions." The extent to which tram traffic must be guaranteed during the construction period will be continually coordinated with the BVG.
However, this variant performs worst in the environmental test. Especially because 120 trees have to be felled for this - the highest number of all variants. However, even for the most tree-friendly variant, 80 specimens would have to give way.
The new Belt Road Bridge will be around 20 meters longer than the existing structure, which is around 47 meters long. The Senate ordered this so that the tram and the two car lanes in each direction can be separated from each other on a longer section of the road than before. The replacement of this bridge is expected to cost around 73.5 million euros.
“Due to their large dimensions, the arch bridges must be installed in the immediate vicinity of the installation site.”
The two tied arch bridges are to be pre-assembled at the same time on an area east of the tracks and the Belt Road and lifted into place over a weekend. “Due to their large dimensions, the arch bridges must be installed in the immediate vicinity of the installation site,” it says in the documents. A lot of trees have to fall for this assembly site, which is around 140 meters long and 20 meters wide.
The new bridges over Wartenbergstrasse and Tasdorfer Strasse are much more prosaic. They are to be rebuilt as reinforced concrete frame bridges. Expected costs for this are not mentioned. Precautions are also being made on the railway embankment for a possible route for the extension of the A100 urban motorway, the possible exact location of which is not yet known.
Not only will the bridges change the look of the area, but also the planned noise protection. To the east of the tracks, six meter high noise barriers are to be built over 454 meters. To the west of the tracks it should be 513 meters, with a height of three to six meters.
The 14-month closure will be a major turning point, especially for the S-Bahn. 630 trains pass through the section every day on lines S41, S42, S8 and S85.
To ensure that as much traffic as possible can be maintained during the construction period, a double track change is to be installed north of the Frankfurter Allee S-Bahn station. A temporary turning point is to be built north of the Ostkreuz. However, it can still be assumed that not all trains will reach these two stations. During rush hour there are currently three trains in each direction every ten minutes - too many for stable operation.
The affected long-distance railway tracks are only used for operational journeys by long-distance trains and a few freight trains per day. The route connects the tunnel part of the main station to the Rummelsburg ICE depot via the shortest route. However, the Ringbahn tracks are repeatedly used to divert regional trains when other routes are closed. The RE2 trains are currently running here due to the closure of the light rail line. The airport express FEX used the route until the Dresden Railway opened at the end of 2025.
The 14-month closure can certainly be a challenge for Deutsche Bahn’s operations. ICE trains arriving and departing will have to take long detours over routes that are sometimes very busy. The “ICE pit stop” planned by the DB in Berlin-Schönholz could offer relief. But the status of the project is unclear. The last entry on the website about the project is from July 2024. The commissioning in 2026 announced in 2021 is in any case obsolete.
Objections to the project can be raised as part of public participation until December 21, 2026.