traffic | Horror show of regional train traffic in Berlin and Brandenburg

Deutsch (original) ·Auto-translated to English

Problem train on a problem route: Pesa Link on the RB26 near Obersdorf Photo: Nicolas Šustr Things are not going smoothly in rail traffic in Germany. High demand meets a crumbling infrastructure with many disruptions, spontaneous construction sites and construction time extensions. There are also vehicle problems that affect both the availability of existing fleets and, in some cases, years-long delivery delays for new trains.

The reports about the difficult situation and its causes also fill a large part of the regional train passenger talk day in Berlin and Brandenburg on Monday evening in the Citizens' Hall of the town hall in Berlin-Zehlendorf. The organizer, the Berlin passenger association IGEB, brought representatives from the DB Regio, the Niederbarnim Railway (NEB) and the East German Railway (ODEG) as well as the Berlin-Brandenburg Transport Association (VBB) to the stage.

ODEG operations manager Lars Gehrke finds the clearest words. After all, he begins his lecture with “really good news” about the RE1 regional express: According to current information from Deutsche Bahn, the platform extensions in the eastern section of the line between Berlin and Frankfurt (Oder) should actually be ready in time for the timetable change on December 13th. This means that the trains, which have been extended from six to eight cars, can then stop at all stations except Briesen (Mark). Only the six-car train Magdeburg – Eisenhüttenstadt, which runs once an hour, will continue to stop in Briesen.

The recommissioning of the Berlin light rail system, which is also planned for the timetable change, also ends the division of the line into an eastern and a western section. This means that there will be three trains per hour in each direction during rush hour, which has not been the case for a long time due to other construction sites.

But even with the RE1 the joy is not unclouded. Since the Berlin-Hannover ICE route was completely closed in October, long-distance and freight trains rerouted to the Magdeburg route have caused many delays on the western branch of the RE1. Punctuality is “at rock bottom,” says ODEG managing director Gehrke.

With the reunification of the line in mid-December, this should also have an impact on the East. Contrary to the original announcement, the direct route to Hanover will remain completely closed until the end of 2027.

Gehrke calls the delays in the northern section of the RE8 between Berlin and Wismar “truly catastrophic.” The RE8 runs over the ICE route Berlin-Hamburg, which was closed until mid-June due to general renovation in Brandenburg.

“We had a new infrastructure and everything collapsed,” said the ODEG man. While punctuality previously fluctuated between 75 and 90 percent, in June it also fell to 65 percent in the southern part towards Elsterwerda. After a short recovery to values ​​of up to 80 percent, a third of the trains were delayed again in October. This is probably also related to the problematic situation in Berlin's north-south tunnel, where long-distance connections have been redirected due to the light rail closure.

To date, the signaling technology on the completely renovated route to Hamburg has not regained its full functionality and reliability. Gehrke is also surprised at the misuse of the additionally built platform in Wittenberge on track 6.

"I'll be completely honest: If I lived in Beelitz and had to drive the RB37, I would work from home or buy a car," he says about the ODEG line that connects Beelitz-Stadt and Berlin-Wannsee. Or rather should connect. Because many trips are canceled or do not reach Berlin at all.

"I'll be completely honest: If I lived in Beelitz and had to drive the RB37, I would work from home or buy a car."

Here it is the newly purchased Lint 51 diesel multiple units from the manufacturer Alstom that are causing the problems. “There are no problems that do not exist in these vehicles,” says Gehrke and presents a list of a whole range of problems. The return to service of the Stadler Gtw 2/6 diesel multiple units originally used there from January should provide relief.

When the timetable changed in December, Roman Iwer from NEB operations management promised an improvement for the RB26 from Berlin to Kostrzyn. Then ten of the eleven Pesa Link vehicles should be available again and can be driven in double traction. The trains never achieved the promised reliability. In addition, there were ongoing problems with coupling cars. The result was and is regular overcrowding, delays and cancellations on the connection, which is also used by commuters from Poland.

In addition, there is numerous construction work by network operator DB Infrago on the route as well as long-lasting disruptions. A defective switch at the Biesdorfer Kreuz caused problems for six weeks, and the Küstrin-Kietz signal box was often unmanned. Because damage to the platform in Golzow has not been repaired for almost two months, double trains cannot stop there.

The NEB also has difficulties with its battery trains. Train drivers often forget to lower the pantographs when the overhead line ends. This leads to destroyed pantographs and overhead lines. We are also working on technical solutions to support train drivers.

Fast charging in terminal stations is also not yet possible as planned due to technical issues. This causes delays, particularly on the RB36 between Königs Wusterhausen and Frankfurt (Oder), because the trains have to stand longer to charge enough energy to cover the route.

The recent purchase of a workshop in Elstal by the NEB at least ensures greater maintenance capacity for the battery trains. Apparently there were problems with maintenance at the DB Regio factory in Berlin-Lichtenberg, which was actually in charge of this.

Vehicle problems also plague the DB Regio. With the new north-south transport contract, twelve new double-decker multiple units from Stadler Rail were actually supposed to take over operations on the RE3 line. But the Kiss vehicles should not be available until the end of 2027 – a year later than agreed.

Stadler has a full two-year delay in delivery of the four-part two-system Flirt XL trains ordered for the RE9 for use in Germany and Poland. Since the expansion and electrification of the German section of the route to the Polish border is not due to be completed until the end of 2028 after a recently announced postponement of another year, that's not so bad. The Polish section to Szczecin is currently expected to be completed in 2030.

Trains with locomotives and five double-decker cars will be used on all lines – RE3, 4, 5, 9 and 20. Some of them were withdrawn from the regional train routes RB24 and 32, which will instead be operated with single-deck Talent 2 trains with eight cars. The new RE9 will initially only run between Angermünde and Berlin and will be linked there with the RE20 to Cottbus.

At the passenger speech day, Birte Enzenberger from DB Regio Nordost draws attention to the large increases in passenger numbers on cross-border regional express lines. The number of passengers on the RE10 from Frankfurt (Oder) via Cottbus to Leipzig has doubled since 2019. The RE7 from Dessau via Berlin to Senftenberg has seen a passenger increase of 44 percent since 2023. Enzenberger attributes the increases to the cheap Germany ticket.

The light rail closure has had a positive effect on the punctuality of the RE7, which is now divided into an eastern and a western section. Until the lockdown on June 13th, it was 74 percent in 2026, then it suddenly rose to an average of 91 percent since then. Enzenberger blames the “very long route” of the line for this.

Patrick Fiedler, head of the offer planning department at VBB, promises changes. The line could therefore be divided and reconnected in Berlin. However, since discussions are still ongoing, he cannot say anything more precise at the moment.

This article cost you nothing. Us: research, production and technology. We saved on office rent as well as printing and distribution. And we gave up salary. Nevertheless, the calculation doesn't work without you. We need 300,000 euros by the end of the year. You pay what you can, in return we keep writing.